Set Target Dates (3 Steps)

Step 1:
Highlight the tasks in the Project that are to have Target Dates set. Right-click on the selected list and select Set Targets > Set Target Start to > Forecast Start (or enter a date manually).

Step 2:
Right-click on the list again and select Set Targets > Set Target End To > and select one of the Forecast End dates (or enter a date manually).
Step 3:
The Target Dates are now set and status decorators will be shown on the task icon